First I do
Code: Select all
S1..S4 = T / 4
After that I only need to split the remainder evenly to some of the stations. I do
Code: Select all
R4 = T % 4
Split3 = R4 / 3
S1..S3 += Split3
In a next iteration I do
Code: Select all
R3 = R4 % 3
Split2 = R3 / 2
S1..S2 += Split2
In the last iteration I just do
Code: Select all
R2 = R3 % 2
S1 += R2
This is how it looks:
And this is the blueprint:
Do you have any ideas/knowledge if this can be done with less combinators? Thanks!